Tackling hydrogen refuelling
10 January 2025

The transportation and supply of hydrogen on site have been identified by Balfour Beatty as being among the main challenges when using the fuel in its ongoing M77 Hydrogen research project in Scotland.
For one thing, the transient nature of the construction industry does not fit the current hydrogen rollout model, where investors and suppliers seek guaranteed consumers (known as off-takers) within the local area via dedicated pipework.
As mentioned previously on the blog, Balfour Beatty is working with suppliers to address this and to ensure they understand the importance of mobile hydrogen deliveries to its construction sites.
Balfour Beatty’s green hydrogen power supply for the project is currently provided by PlusZero Power via the Aberdeen City Hydrogen Energy Storage (ACHES) facility operated by Aberdeen City Council. However, there is no backup supply if this facility requires maintenance or repair.
At the beginning, the project primarily relied on permanent fuel stations or off-site refuelling at suppliers’ facilities. While these options are suitable for HGVs delivering goods across the country, the preferred refuelling model for construction plant and equipment is on-site refuelling.
This is because some plant currently cannot operate on public highways and off-site refuelling causes costly downtime. Moreover, for projects maintaining public highways, on-site refuelling ensures access to fuel in extreme weather (as has been experienced recently) to keep roads open and safe.
Consequently, Balfour Beatty has focused efforts on working within its supply chain to develop a mobile refuelling model that can be set up on temporary sites. It says it has considered a number of refueller units including the Logan Energy refueller, the Hydrasun mobile refueller and the Nanosun Pioneer unit.
Their suitability depends on the end use and likely volumes, with a key learning from the project being that the refuellers can have a significant lead-in time. Ultimately, only the Logan refueller was deemed suitable in meeting the required programme time frames.
For more details of the M77 Hydrogen project, see the earlier blog post here.