Sizewell concrete reuse brings benefits
24 November 2025

An innovative circular economy arrangement between Nuclear Restoration Services (NRS) at Sizewell A and Sizewell C is reported to be delivering savings and reducing carbon emissions.
The turbine hall at the Sizewell A former nuclear power station in Suffolk has been demolished by NRS allowing more than 15,000 tonnes of crushed concrete from the turbine alternator plinths to be reused in building the new Sizewell C facility.
All recycled materials have been transported just a few hundred metres up the coast to Sizewell C’s main construction area (MCA), where they are being repurposed as sub-bases for various foundation platforms. The collaboration significantly reduces shared costs and carbon emissions, and the need for newly mined aggregates.
Damian Leydon, Site Delivery Director at Sizewell C, said: “This is another example of how Sizewell C is working with local projects to maximise benefits, not just for us, but for the local community. By reusing this material, we’re reducing the number of trucks transporting aggregate through East Suffolk, while further reaffirming our commitment of minimising our environmental impact during construction.”
Wendy Heath, NRS Senior Project Manager at Sizewell A, said: “This innovative approach has prevented 28 tonnes of CO₂ emissions by diverting waste from landfill, completing the circular economy for this material. This marks a first-of-its-kind achievement for NRS and showcases how collaborative working is enabling sustainable decommissioning. By reducing waste and minimising traffic on local roads, we’re actively supporting the future of clean energy.”
Senior representatives from the Environment Agency and the local authority approached the Sizewell C project team with the opportunity to repurpose this material, which would otherwise be treated as waste.
Since September, Sizewell A has been carrying out the crushing, testing, and certification of the concrete to ensure it meets the WRAP (Waste and Resources Action Programme) quality protocol. Once certified, the material has then been transported to the Sizewell C site as recycled aggregate.
The initiative has reduced site traffic on local roads, as almost 800 vehicle movements will be confined to the vicinity of Sizewell A and Sizewell C.
Councillor Tom Daly, East Suffolk Council Cabinet Member for Energy and Climate Change, said: “I am pleased that material from the decommissioned Sizewell A power station is being reused for Sizewell C. It’s vital that every effort be made to minimise the impact of construction on the environment and local community.”