Hydrogen trial shows promise
27 June 2025

A trial of equipment using solar and green hydrogen energy by the Kier Group and the Environment Agency in Somerset has yielded positive results in its first months.
The minimum 12-month trial is designed to explore whether solar power with a green hydrogen backup is a viable primary power supply on a construction site where access to mains electricity is not available.
The on-site welfare and office facilities at the Bridgwater Tidal Barrier scheme were selected for the trial, with the hope that data will inform whether this approach is feasible and scalable for the demands of large-scale construction sites.
From the start of January to the end of April 2025, a total of 16,047kWh has been used at the site. This comprises 6,588kWh from solar power, 9,171kWh from green hydrogen and 287kWh from the back-up batteries.
When compared against an equivalent diesel generator to run the site with no additional interventions, the trial has generated estimated savings of around 20,000 litres of diesel, resulting in approximately 53,000 kgCO2e (carbon dioxide equivalent) avoided at the point of use. This is said to be equivalent savings of 195,000 miles in an average diesel car or 350 one-way flights from London to Glasgow.
As well as contributing to a reduction in carbon emissions, the equipment reduces noise levels on site for people and wildlife, and avoids the potential spill risks associated with diesel generators.
Jo Driffield, senior engineer within the Environment Agency Innovation Team, said: "This trial is a big step forward to help the Environment Agency realise our net zero goals and a sustainable future. Conducting trials like this will demonstrate the demand for hydrogen, especially green hydrogen, which is needed to help support the investment into the production and supply to the construction industry and other uses."
Working with the specialist supplier TCP Group, learnings from the planning, initial setup and real-time tracking of energy usage data monitoring have already been applied. This includes adding another fuel cell, using air conditioning units and responding to requests from the site team to add energy usage data to site internal communication platforms as part of sharing performance and encouraging behavioural change.
Andrew Barker, Managing Director, TCP Group, said: "We’re proud to be collaborating with Kier on this vital project in Somerset. As our largest-ever hybrid hydrogen solution for site welfare installed to date, it’s already proving a fantastic opportunity to collaborate and help shape energy conservation practices based on robust data monitoring."