Energy island

1 January 2025

Energy island

Since the start of 2024, what has been described as the world’s first energy island has been under construction in the Princess Elisabeth zone off the Belgian coast in the North Sea.

The six-hectare Princess Elisabeth Island will serve as an energy hub from about 2030 providing a significant contribution to Europe’s sustainable energy supply.

The facility is being erected on a total of 23 caissons, each approximately 60m long, 30m wide and 22m high. More than 120 Wacker Neuson IRFU high-frequency internal vibrators have been used in their manufacture, powered by the company’s ACBe battery backpack.

Each caisson is poured 24 hours a day over seven to eight days, during which time it is necessary to continuously consolidate the concrete. The interchangeable nature of the batteries means that work can continue uninterrupted, with no trip risks caused by cables running along the ground or in wet concrete. The batteries can also be used to power other items of equipment.

● Subscribe to the blog to receive regular updates here.


Subscribe

I am constantly adding new content. If you subscribe FREE using the form below, I'll send you my weekly bulletin summarising the latest hire industry stories - and I'll also send you a PDF of 10 fascinating interviews with national and independent hirers, giving their views about business and their secrets of success!